JOB-PORTAL
JOB-PORTAL
    Portale del lavoro
    Vacatureportaal
    Portal del empleo
    Portal pracy

Grid Connection for PV, BESS, and Wind

We support you with the grid connection of PV, BESS, and wind projects – from the initial application to the grid operator, through grid connection planning, to quality assurance for the construction of substations and transfer stations.
This ensures that grid operator requirements are understood early, decisions are transparent, and interfaces are properly prepared.

Inquire NowLearn more

Grid Connection & Integration

We ensure that your PV system, battery storage (BESS), or wind power  plant (WPP) is optimally integrated into the power grid – from the initial non-binding grid connection application, grid connection design, support with the procurement of transformers, substations, and calbles to quality assurance during the construction of the grid connection.

We identify potential grid connection points, submit non-binding grid connection applications, and undertake – in accordance with all grid operator specifications – the appropriate grid connection design with a comprehensible design for connection to medium or high voltage. We review existing grid connections for optimisation potential, evaluate flexible grid connection agreements (FCA) for your project if necessary, and support you in negotiations with the grid operator.

Our work helps you avoid surprises when connecting to the power grid, allows for realistic project cost calculation, and lays the foundation for stable and reliable operation of your system.

grid integration overhead line

Grid Connection & Integration by Technology

PV

Non-binding grid connection application for photovoltaic projects including documentation package and submission
Review of existing grid connection points and technical consultation on optimization possibilities or flexible grid connection agreements (FCA)

Preliminary or detailed / electrical grid connection design “from the inverter to the grid connection point” – including single-line diagram (SLD) and metering concept

BESS

Non-binding grid registration for battery storage (stand-alone or co-location) including documentation package and submission
Review of existing grid connection points and technical consultation on optimization possibilities or flexible grid connection agreements (FCA)

Preliminary or detaild / electrical grid connection design”from the inverter to the grid connection point” – including single-line diagram (SLD) and metering concept

Wind

Non-binding grid registration for wind power plants (WPP) including documentation package and submission

Review of existing grid connection points and technical consultation on optimization possibilities or flexible grid connection agreements (FCA)

Preliminary or detailed electrical grid connection design from the turbine termination point to the grid connection point – including single-line diagram (SLD) and metering concept.

When grid connection services from greentech are the right solution for your project

If you need early guidance on connection options.

Location and capacity are roughly determined, but you need to quickly know which grid connection points are realistic and what the next step looks like.

If you want to structure communication with the grid operator.

Inquiries, documents, and technical requirements should be clearly bundled to enable faster and more consistent decision-making.

If you require reliable preliminary design for the grid connection.

From “connection generally possible” a technical concept should emerge – e.g., as a basis for project calculation and subsequent planning decisions. The preliminary design clarifies key aspects (connection variant/voltage level, central components, interfaces) and aligns them with grid operator specifications before you proceed to detailed planning.

If there are restrictions at the grid connection point (power, reactive power, feed-in requirements).

Grid operator requirements influence design or economic viability – an early technical assessment and variant evaluation provides clarity.

If you want to specifically examine grid connection optimisation before planning "too far ahead."

You want to compare options (e.g., connection variant, dimensioning, metering/concept approaches) to reduce costs, risks, and re-planning, or you want to cooperate with other developers or operators.

If you need a professional sparring partner for grid topics and communication with the grid operator.

Technical topics (requirements, design, metering/protection/control concept) should be professionally classified, inquiries structured, and your interests effectively represented in discussions.

If your project changes – and grid integration needs to be properly adjusted.

For adjustments to capacity, technology (PV/BESS/Co-location), or schedule, we help identify impacts early and clearly define the next steps.

If you want to reduce planning risks before proceeding to detailed design.

You want to prevent later planning stages from having to be re-initiated due to grid restrictions or unclear specifications.

If you want to evaluate flexibility as an option (e.g., FCA) and realistically assess opportunities.

You want to understand if a flexible grid connection approach is generally suitable and what prerequisites typically need to be met.

Substation engineering – if grid connection is only possible via a dedicated substation

If grid connection can only be realized through the construction of a dedicated substation, the substation becomes the central point of technical design and implementation.

With our implementation package for substations, we bundle the relevant engineering services into a continuous service chain – from preliminary design, through permitting design & documentation, to the detaild electrical design of the connected system(s) (PV, wind, and/or BESS) as a technical basis for substation design and interfaces. We consider SCADA and control requirements from the outset – including implementation via the “greenCORE” power plant controller. Building on this, we prepare the tender documents for the substation and transformer, support contract negotiations, and accompany the implementation on site until acceptance.

This provides you with a consistent technical basis, clear interfaces, and documents that can be directly used for project implementation – without discontinuities between grid requirements, design, procurement, and commissioning.

Further information on our services for the planning and construction of substations can be found here:

\

Site and Route Analysis

\

Design Planning & Yield Simulation

\

Technical EPC Tender

\

Building Permit Documents

\

AC Electrical Planning of Systems to be Integrated

\

SCADA & IT Planning and Implementation

\

Construction and Acceptance Support

substation planning

What distinguishes our grid connection services?

Icon with forward arrows

Holistic grid perspective

We view grid connection, system design, and regulatory requirements as an integrated system. This allows you to identify technical interdependencies early and make informed decisions for your project.

Icons for financial returns

Early planning assurance

With our concepts, you gain clarity on realistic connection options already in the development phase. Potential bottlenecks or conflicts with grid operators become visible early – before they impact the schedule and project costs.
Icon with certificate

Economic reality check

As part of our grid connection design, we evaluate not only technical feasibility but also the economic implications of various connection options. This provides you with a reliable basis for the costs, efficiency, and long-term economic viability of your PV, wind, or storage project.

Overview of our services

Our services bundle the central steps necessary to technically connect a PV, wind, or storage system to the power grid – from initial orientation in the early project phase to a reliable basis for further planning. We handle structured communication with the grid operator and prepare the necessary documents so that you can make informed decisions. Our services can be commissioned individually – depending on your project phase and existing results.

Non-binding grid connection application

The preparation of the non-binding grid connection application (grid registration) ensures that your project is correctly addressed to the responsible grid operator early on and that you receive reliable initial feedback on the next steps. Upon request, we can also provide further technical support – including tracking the grid application process and coordinating with the grid operator.

 

  • Identification of responsible grid operators
  • Compilation and preparation of required documents
  • Completion of grid operator-specific forms
  • Submission of grid registration
  • Feedback

Grid connection design

Both preliminary and detailed electrical design of the grid connection are elementary components of project planning. Based on your designed photovoltaic, wind power, or battery system and the grid operator’s specifications, we select the correct grid connection components, including route cables, transformers, as well as metering, protection, and control technology, and perform load flow and short-circuit current calculations.

The preliminary design defines the grid connection concept and key parameters; the detailed design (AC electrical design) elaborates these contents to the level of detail required for construction and procurement. The core components remain the same but are finalized and prepared for implementation in the detailed design.

Grid connection optimisation

Grid connection optimisation starts where a grid connection point is generally feasible, but the boundary conditions are not yet “ideal” – e.g., due to limited connection capacity, requirements for feed-in/reactive power, or technical and economic trade-offs in the AC connection. We analyze the existing initial situation (project assumptions, grid operator feedback, planned mode of operation), derive concrete optimisation levers, and evaluate variants to provide you with a comprehensible decision-making basis for further action. The goal is to classify grid restrictions early, avoid unnecessary planning detours, and establish robust grid integration early on. Optionally, consultation on flexible grid connection agreements (FCA) may be useful if flexibility is a realistic lever for project development. 

  • Analysis of grid boundary conditions and grid operator feedback (e.g., connection capacity, voltage level, specifications)
  • Identification and evaluation of optimization options at the grid connection point (technical and economic)
  • Comparison of variants including impacts on concept, cost/risk assumptions, and further planning steps
  • Recommendation for a reliable approach (incl. coordination and decision points)
  • Optional: FCA consultation as a next step (classification of opportunities, prerequisites, and implications)

Components of Grid Connection Planning

The single-line diagram (SLD) is not only a central component for system certification but also serves as a basis for tendering system components or as a source for fault analyses during later operation. It provides information on the installed generation units, the design of high- or medium-voltage transformers, cable lengths and types, inverter data, or protection and control devices. As part of grid connection planning, we map the planned system design in DIgSILENT PowerFactory software and determine the required designs of the individual system components. We also review and advise on existing single-line diagrams as Owners Engineer.

 

Creation of a single-line diagram (SLD)

Often, the energy transmission losses of the system, for example from the inverters to the grid connection point, are only estimated broadly during project development. This can lead to discrepancies between the planned and actually produced electricity later on, which in turn can affect the economic viability of the system. We calculate active power losses both system-specific and project-specific, and as part of grid connection planning, we ensure that transmission losses are accurately represented while economically designing components.

Calculation of active power losses

As a complex topic with many unknowns, greentech’s grid connection engineers shed light on the reactive power complexities of your photovoltaic system. They consider the individual requirements of the grid operator and make the concrete net feed-in capacity of the system transparent. This allows necessary changes to the system design, such as determining the number of inverters required for the demanded reactive power, to be made during the development phase to meet the grid operator’s later reactive power requirements. This ensures your system project remains economically realistic. Surprises from feed-in limitations during system certification are avoided.

Reactive power calculation

Photovoltaic systems must be “thought of” over a period of several decades. While there were hardly any systems outside of EEG remuneration in the past, projects today can successfully produce electricity economically even without state tariff guarantees, for example through power purchase agreements (PPAs). Hybrid models are also in operation today, where the respective amounts of electricity produced must be precisely verified. For systems increasingly planned as co-location with connected storage, precise measurement of the incoming and outgoing electricity quantities is also relevant. Therefore, a future-oriented metering concept for the system should be considered from the outset. As part of grid connection planning, we create an individual metering concept for you, avoiding cumbersome retrofitting measures later on.

 

Creation of metering concepts

Creation of a single-line diagram

The single-line diagram (SLD) is not only a central component for system certification but also serves as a basis for tendering system components or as a source for fault analyses during later operation. It provides information on the installed generation units, the design of high- or medium-voltage transformers, cable lengths and types, inverter data, or protection and control devices. As part of grid connection planning, we map the planned system design in DIgSILENT PowerFactory software and determine the required designs of the individual system components. We also review and advise on existing single-line diagrams as Owners Engineer.

Calculation of active power losses

Often, the energy transmission losses of the system, for example from the inverters to the grid connection point, are only estimated broadly during project development. This can lead to discrepancies between the planned and actually produced electricity later on, which in turn can affect the economic viability of the system. We calculate active power losses both system-specific and project-specific, and as part of grid connection planning, we ensure that transmission losses are accurately represented while economically designing components.

Reactive power calculation

As a complex topic with many unknowns, greentech’s grid connection engineers shed light on the reactive power complexities of your photovoltaic system. They consider the individual requirements of the grid operator and make the concrete net feed-in capacity of the system transparent. This allows necessary changes to the system design, such as determining the number of inverters required for the demanded reactive power, to be made during the development phase to meet the grid operator’s later reactive power requirements. This ensures your system project remains economically realistic. Surprises from feed-in limitations during system certification are avoided.

Creation of metering concepts

Photovoltaic systems must be “thought of” over a period of several decades. While there were hardly any systems outside of EEG remuneration in the past, projects today can successfully produce electricity economically even without state tariff guarantees, for example through power purchase agreements (PPAs). Hybrid models are also in operation today, where the respective amounts of electricity produced must be precisely verified. For systems increasingly planned as co-location with connected storage, precise measurement of the incoming and outgoing electricity quantities is also relevant. Therefore, a future-oriented metering concept for the system should be considered from the outset. As part of grid connection planning, we create an individual metering concept for you, avoiding cumbersome retrofitting measures later on.

FAQ: Grid Connection & Integration

Frequently Asked Questions about greentech’s grid connection services

What does grid connection design at greentech include?

We support you through the central steps to properly connect PV, wind, or BESS projects to the power grid: from grid registration and technical classification of grid requirements to grid connection design and optimization. The goal is to make grid operator specifications comprehensible early on and to prepare them as a reliable basis for your next project decisions.

What does the creation of a non-binding grid registration (grid connection application) entail?

We identify the responsible grid operators, compile the necessary documents, complete grid operator-specific forms, and submit the grid registration. You receive feedback on the status, e.g., including confirmation of receipt. Optionally, you can also commission technical consultation and further support for coordination with the grid operator.

When is a non-binding grid connection application useful?

A non-binding grid connection application is particularly suitable in the early project phase. It provides a realistic assessment of possible grid connection points, evaluates the appropriate voltage level, and provides information on the connection possibilities of your project.

When do I need preliminary design for the grid connection?

As soon as “connection generally possible” needs to become a reliable basis for project calculation, further planning, and technical decisions. Preliminary design helps to verify central assumptions early and avoid later re-planning when grid operator requirements become concrete.

What does grid connection optimisation mean in practice?

Grid connection optimization means that we translate an existing grid connection point and its associated boundary conditions into concrete, comparable variants – and derive a clear recommendation from them. For this, we look at, for example, where the bottlenecks lie (connection capacity, reactive power requirements, operating limits at the grid connection point) and which technical levers are realistic. The result is not a “general consulting paper,” but a structured decision-making basis on which connection and concept variant is most sensible under your project goals – including the most important assumptions, open points, and the next steps for coordination with the grid operator.

Does greentech support communication with the grid operator?

Yes. We structure inquiries and documents, classify technical requirements, and take on the technical part on the client’s side. This allows grid-related issues to be clarified efficiently – with clear lines of argument and clean documentation of assumptions.

What are the core components of grid connection design?

Grid connection design at greentech comprises four central components:

  • Creation of a single-line diagram (SLD)
  • Calculation of active power losses
  • Reactive power calculation
  • Creation of metering concepts

How does greentech consider grid connection design for PV, wind, and BESS in co-location projects?

We approach grid integration across technologies and consider the respective requirements of the system(s) to be connected. For co-location, it is particularly important that interfaces, operating assumptions, and metering/control approaches are consistently set up so that grid requirements and project logic align.

Does greentech have to implement the grid connection design?

No, we provide a well-founded concept and all necessary plans and calculations. These can be directly used by an EPC or project partner for electrical design according to grid code – or we can gladly carry them out for you.

When is flexibility (e.g., FCA) a sensible next step?

If connection capacities are limited or restrictions at the grid connection point affect project development, flexibility can be an option. We support in assessing the general suitability, clarifying prerequisites, and deriving the next steps in a structured manner.

When do I need a dedicated substation – and how does greentech help?

A dedicated substation becomes relevant if the grid connection can only be realized via an appropriate transfer/transformation level. We offer an implementation package for this – from preliminary design and permitting design & documentation to technical concept (incl. SCADA/control) to EPC tendering and construction/acceptance support – so that design, procurement, and implementation work together seamlessly.

Still have questions?

Can’t find the answer you’re looking for? Please get in touch with our team of experts

Engineering & Technical Advisory

 

Here you can download an overview of our Engineering & Technical Advisory services:

greentech overview-engineering services

Why work with greentech?

Icon of greentech.energy's experience

Years of experience
Icon for team size

Employees active in 6 European countries
Icon for the number of projects

Projects in the development pipeline
Icon number of ground-mounted PV systems built

Ground-mounted PV systems built
Icon for the number of projects

in technical consulting
Icon for team size

in operational management

Your Specialists for Grid Connection & Integration at greentech

Expert: PV yield assessment
Viola Hoffmann

Commercial Head of Engineering

As Commercial Head of Engineering at greentech, Viola Hoffmann is responsible for the commercial management of the engineering department. In her role, she connects technical project requirements with economic implementation – from offer and project costing to the further development of suitable commercial services within the engineering context. Viola Hoffmann has been active in the solar industry since 2017. She studied European Studies as well as International Business Administration and Politics (among others in the Netherlands and Copenhagen) and also brings experience from entrepreneurship and working in young, dynamic companies.
Johannes Liebich

Head of Engineering & Technical Advisory

Johannes Liebich is head of the “Engineering & Technical Advisory” team at greentech. He is responsible for the planning and implementation of projects and for the development of new services in technical plant consulting. Johannes Liebich studied Environmental Engineering with a focus on photovoltaics and has been working in the solar industry since 2011. As an experienced Technical Advisor, his main focus is on plant construction and operation.
Joern Carstensen Chief Technical Officer (CTO)
Joern Carstensen

Chief Technical Officer (CTO)

In his role, Jörn Carstensen combines the management of all technical areas of the greentech group. As CTO, he is responsible for plant construction, engineering services and technical management. The aim is to create uniform standards and processes across all technical areas at greentech, thereby ensuring company-wide synergies, high quality and the greatest possible transparency.

Jörn Carstensen joined greentech in 2014 as Business Development Manager. In addition to developing various European markets, he built up the Engineering and Technical Advisory division. From 2006 to 2014, he worked for the Conergy Group in various international corporate and business development positions. Prior to that, he worked for a consulting unit of Accenture and supported utility companies in strategic and organisational issues. Jörn Carstensen holds a degree in Industrial Engineering with a specialisation in Energy and Environmental Management from the Universities of Flensburg and Southampton.

Contact

Only 45 seconds for your request

Loading

You might also be interested in

Potential Analysis

Detailed Planning